US 41 and SR 54: What FDOT’s plans show for nearby businesses
Aerial footage by Jimmy Schaefer for Voyuno.
FDOT’s approved June 2026 environmental report anticipates 88 business displacements. A closer look at the drawings, familiar locations and questions still ahead.
By Jimmy Schaefer | Voyuno
If you’ve waited at the light at US 41 and SR 54, you’ve driven past the businesses FDOT’s interchange plan could affect.
The project’s approved June 2026 environmental report anticipates 88 business displacements, four residential relocations and the displacement of one publicly owned facility. Those are planning estimates, not closure notices.
I filmed the intersection from above for Voyuno’s coverage. Paired with FDOT’s drawings, that view helps explain why the project could change more than your commute—and why some businesses are affected by proposed ponds as well as new lanes.
Watch the intersection story
Loading YouTube post…

FDOT March 2026 concept, cropped for context. Business labels reflect the drawing, not a verified current tenant list. Open the complete FDOT plan.
What FDOT has accepted
FDOT reports that the project received Location and Design Concept Acceptance on June 10, 2026. The preferred concept is a diverging diamond interchange, with US 41 elevated over SR 54 and Dale Mabry Highway.
FDOT describes the project’s purpose as increasing capacity and reducing congestion. Its website links the accepted concept drawings, where readers can inspect the proposed ramps, crossings and surrounding land uses.
Concept acceptance is an important milestone, but it is not a notice that construction is starting immediately. The sources reviewed here do not establish individual business move deadlines.
Questions neighbors are asking
When I shared this story on Nextdoor, neighbors had plenty of questions. Here is what FDOT’s published project pages and documents say about the ones they can answer—and where they stop.
Why elevate US 41 instead of SR 54?
FDOT’s January 2026 evaluation matrix compared a no-build option with two build options: SR 54 over US 41, and US 41 over SR 54, which is the preferred alternative. A few of the figures it lists:
- SR 54 over US 41: 36 business relocations, 4 residential relocations, 116.60 acres of right of way and an estimated total project cost of $596.52 million.
- US 41 over SR 54: 97 business relocations, 4 residential relocations, 44.03 acres of right of way and an estimated total project cost of $489.49 million.
The matrix also compares noise, floodplain, wetland and contamination factors. It shows the trade-offs, but not how FDOT weighed them; for FDOT’s own explanation, see the project documents linked below. One note: the matrix’s 97 business relocations is a different January figure than the 96 in the relocation plan discussed below, and the documents reviewed do not explain the gap.
What is the project meant to fix?
FDOT says the project is meant to address future roadway capacity issues and improve safety. Its project page also points to future traffic demand and population and employment growth, and notes that SR 54 is a primary evacuation route. The preferred alternative is a diverging diamond interchange with US 41 elevated over SR 54 and SR 597, which is Dale Mabry Highway.
Are homes affected?
FDOT’s evaluation matrix lists four residential relocations for each build option, and the June environmental report anticipates four residential relocations for the preferred concept. Those are planning estimates. If you live near the intersection and want to know how the plan affects your property, FDOT’s project team is the place to ask (contact details below).
When would any of this happen?
When I checked FDOT’s project schedule page on October 24, 2026, it listed design for 2025–2027 and right-of-way acquisition for 2028–2030, with construction marked “Currently Unfunded.” The same page says all information is preliminary and subject to change without notice.
Who do I ask at FDOT?
FDOT’s project page lists Andrew Williams, P.E., PD&E Project Manager at FDOT District Seven, as the contact for questions and comments: (813) 975-3698 or [email protected]. The page also says technical reports and engineering documents can be requested from the project manager.
Have a question the documents don’t answer? Email [email protected] and I’ll add it to our list of questions for FDOT.
Why some businesses are under blue or pink—not yellow
The drawings can be easy to misread. Yellow marks proposed roadway. The darker blue/purple marks preferred pond sites. Pink identifies floodplain compensation sites.
Stormwater management facilities handle runoff. Floodplain compensation areas provide storage to offset floodplain storage affected by the project. Both can require land beyond the new lanes themselves.
Near the shopping center labeled “Big Lots,” “Party Liquors” and “Subway” on FDOT’s drawing, a blue/purple area is marked SMF 2D. That indicates a preferred stormwater facility at that location. The drawing also marks a red B with a count of 15 in that shopping-center area. In the legend, B symbols identify potential business relocations.
The drawing uses older business labels. My recent photograph shows Ollie’s signage where the plan still says Big Lots. A location on a concept drawing should not be treated as a verified, current tenant list.

Source: FDOT March 2026 concept. Read land-use colors and relocation symbols together.
Why you may have heard 96 instead of 88
The January relocation report estimated 96 business relocations. The later June approved environmental report states 88 business displacements in Section 3.6.
Voyuno is using the newer report’s figure of 88, with its date attached. The documents reviewed do not explain the difference, and Voyuno has not yet reconciled the January business inventory with that later total. It should not be presented as a final list of 88 current businesses.
Which familiar businesses appear in the records?
The names below come from the January 2026 planning inventory, which predates the June total. They are not a current closure list or confirmation of move notices.
That January plan names Party Liquors and Subway in a 15-business entry at 2416 Land O’ Lakes Boulevard. It separately lists McDonald’s at 2420 Land O’ Lakes Boulevard and 7-Eleven at 2400 Land O’ Lakes Boulevard for anticipated displacement.
MCOR Auto Shop shares a four-business table entry at 21126 SR 54 with Alessi Dance Factory, MÜV Dispensary and Intoxalock. The drawing identifies a floodplain compensation site, FPC 110D, at the MCOR location.
Farther along the corridor, the January table also includes The Breakfast Nook among eight businesses grouped at 1520 Land O’ Lakes Boulevard. The public facility identified in the June environmental report is Pasco County Fire Rescue Station No. 23.
These names come from FDOT’s planning inventory. They do not establish that each business has received a move notice, decided to close or secured a replacement location. Current tenants and individual plans need confirmation with the businesses and FDOT.
The challenge of staying nearby
The June report says available commercial properties within Land O’ Lakes are insufficient to accommodate all displaced businesses. It identifies replacement opportunities in the broader market and says businesses may need to move to surrounding Pasco communities at distances of “approximately seven miles from their existing locations.”
That is an assessment of possible replacement options, not a statement that every affected business will move seven miles. The report also says eligible displaced businesses will receive relocation assistance, including advisory services and financial assistance under applicable requirements. Individual eligibility and benefits need to be discussed with FDOT’s relocation staff.
For customers, the practical question is whether a familiar service will remain convenient—and how to find it if it moves.
Help us tell the business side of this story
If you own or work at a business identified in the project documents, what have you been told directly about the project’s effect on your location?
Email [email protected] to share your business’s experience. Include your business name, location and what you have been told directly about the project. Please keep private notices and personal contact details out of public comments.
For official project questions and contact information, visit FDOT’s project page linked below.
Voyuno’s next reporting step is to seek business-owner perspectives and clarify the remaining questions with FDOT. Confirmed relocation destinations can help neighbors keep supporting the businesses they know.
Share this article with someone who shops, works or operates a business near US 41 and SR 54.
Sources
FDOT project overview: View FDOT source
FDOT final project documents: View FDOT source
Approved Type 2 Categorical Exclusion, June 10, 2026, Section 3.6, printed pages 15–16 (PDF pages 19–20): View FDOT source
Conceptual Stage Relocation Plan, January 2026, Table 2-1 and Table 5-1 (PDF pages 16 and 27–30): View FDOT source
March 2026 concept and legend: View FDOT source
Evaluation matrix, Virtual Project Update, January 28, 2026: View FDOT source
Virtual Project Update (2026) page: View FDOT source
Project schedule: View FDOT source